Brewery News and Plans, Brewery Construction Progress, and Brewmaster's Pintification

Permits for the up fit of 217 South Street have been submitted to the City of Wilson.

As soon as we receive approval to begin the work we will start with installation of the sprinkler system followed by installing the piping for the two HVAC systems. Then move into electrical, plumbing, and framing of various rooms in the building (grain, office, bathrooms, coolers). This should take about 4 months to complete.

The brewing equipment has been ordered and will arrive in late August or Early September.

Assuming all goes well with TTB and construction permits, inspections, and certificate of occupancy, we should be on schedule to open over the Whirligig Festival in November.