The FRP finish was applied to the interior of the coolers and the outside of grain room. It will help keep the coolers cold while keeping the exterior of the “wet" areas of the brewery protected. All 3 ac units are running. We will test those this weekend when we begin to condition the inside of the building for the floor work starting next Monday.

John Kater and I will be ordering some of the additional supplies and equipment needed to begin brewing as soon as the brew house ewuipment arrives.

Chiller is due to arrive either Friday of this week or early next week. Our keg cleaner will ship on the 29th with 6 days in route.

We will be at the building most of Saturday and Sunday painting and getting everything out of the building in prep for the floor work. We will not have access to the building all of next week while the floors are finished.